WARSAW — Progress on reconstruction of two railroad crossings in Warsaw has been delayed.
While Norfolk Southern is still completing improvements to the Market Street crossing, the railroad company said the project has slowed and work on the Winona Avenue crossing has been pushed back to spring 2027.
Officials had hoped to complete both projects by early December.
The city of Warsaw issued an update on Wednesday, saying the completion of the Market Street crossing project has been delayed due to train traffic and weather conditions.
The crossing will be paved after the Thanksgiving holiday weekend when weather and asphalt availability allow. The crossing will remain closed until paving is complete.
Because of the delays and challenges with the Market Street crossing, as well as drastically colder temperatures, the Winona Avenue crossing upgrade will now move to Norfolk Southern’s Spring construction schedule. This change will ensure a quality finished product when the project is completed, the city statement said.
Norfolk Southern has agreed to patch the Winona Avenue crossing to improve driving conditions for the winter months.
Norfolk Southern and the City of Warsaw appreciate residents’ patience as both organizations work together to implement longer-term crossing improvements under unpredictable conditions.